Case Study > Industrial complexes adaptation
Sirp production lines expansion
Cologna Veneta, Verona
Construction of the steel foundation and mezzanine structure for the expansion of the production lines of Sirp spa, a company specializing in leather treatment for the fashion industry.
Client
Year
Status
Value
Team
Sirp spa
2023
Concluded
840.000 €
1 Technical director
13 Skilled laborers
Client
Year
Status
Value
Team
Sirp spa
2023
Concluded
84.000 €
1 Technical director
3 Workers
10 Skilled laborers (subcontractors)
For the expansion of its production lines, Sirp spa relied on Eleva Build to
follow the various phases of the work: from the design of the new spaces, to the demolition of the
existing structures, and construction of the new lines.
All while adhering to set deadlines and objectives, fully respecting the continuity of production of the company.
All while adhering to set deadlines and objectives, fully respecting the continuity of production of the company.
The Project in numbers
Sqm
in total
Months
in total
Persons
employees
Hours
of assembly
First stage
Having demolished the existing slab and performed the overburden excavation, it was possible to
create the new foundation slab: an iron structure designed through a careful
analysis of the interactions between the different structures and the soil. Upon completion of this
first phase on the concrete layer, industrial paving was constructed.
Concrete abutments were made to support the bottoms.
Concrete abutments were made to support the bottoms.
Second stage
The second phase of this extension involves the installation of a technical mezzanine, supplied
and laid by Eleva Build, on which a self-supporting slab with trapezoidal sheet metal was placed
covered with a collaborating hood casting, to consolidate the union between the floor slab and beams.
A gutter was inserted at the edge of the slab that joins with the drainage channels
placed in the slab. The whole was covered with resin flooring.
Print Format
PROJECT FILE
Related Case Studies
Large Surfaces
Torri di Madonna Bianca, Trento
2023
A work of over 8000 square metres of cladding with drywall panels.
Composite wood
finishes
Viale Ortles, Milano
2023
A new identity for the residential complex of Viale Ortles in Milan, thanks to the continuity of finishes that cover the façade.
Retractable glass
wall
Brera, Milano
2023
360° project for the glazed wall vertical retractable glass wall: reconditioning of the structure, to the redesign and engineering of the new system.
Tagged Cologna VenetaVerona